BBI Airport, Berlin Brandenburg

BBI Airport, Berlin Brandenburg, Germany - Only when seen from an aerial perspective is the scale of the construction site really apparent: the area is the size of around 2,000 football pitches.
BBI Airport, Berlin Brandenburg, Germany - The QUATTRO column formwork can be loaded with a fresh concrete pressure of 80 kN/m² which facilitates fast concreting.
BBI Airport, Berlin Brandenburg, Germany - During peak times, approx. 8,000 m² of slab tables were moved to the next place of use per week.
BBI Airport, Berlin Brandenburg, Germany - Where required due to the height of the storey, the formwork was supported by shoring consisting of PERI UP standard components.
BBI Airport, Berlin Brandenburg, Germany - The slab tables were pre-assembled by PERI and delivered just in time to the construction site.

Project data

Location: Berlin, Germany

Terminal for the new Berlin Brandenburg International Airport

Extension area: 970 ha

Requirements

  • terminal shell with a construction schedule of just 12 months
  • huge volume of formwork and scaffolding material within the shortest period
  • due to static reasons, most of the slab areas had to be concreted in one pour together with the main and secondary beams

Customer

BAM Deutschland AG, Stuttgart

Customer's benefit

  • at peak times 8,000 m² of slabs were formed, concreted and realised per week
  • reduced on-site material requirements plus cost savings thanks to coordination by PERI Project Manager in close cooperation with the Site Manager
Jürgen Feierle, Project Manager
Jürgen Feierle
Project Manager

With the PERI slab table solution at peak times we are realising 8,000 m² of slab formwork per week – with all beams and with floor heights of up to 7 m. By combining with SKYDECK we are even able to continue working in strong winds without interruption and can also minimise crane dependency. PERI construction site support offers us technical solutions in the shortest time and also supplies large volumes of materials within just 2 days.

PERI solution

  • delivery of large quantities of materials optimised to the necessary on-site requirements
  • formwork and scaffolding solution for foundations, columns and slabs incl. beams
  • provision of a total of 2,700 pre-assembled slab tables delivered just-in-time to the construction site
  • appointment of a Project Manager to support the Site Manager in planning material requirements