Hongkong-Zhuhai-Macao Bridge (HZMB) | Transitional structure, China

The fabrication of the high side and center walls as well as the breakwaters for two transitional structures is carried out with mobile PERI portal formwork carriages – with a fast cycle sequence and in highest quality.
Side walls and center wall were constructed with the help of three PERI formwork carriages.
Also for the massive breakwater, the construction team used a mobile wall formwork solution.
300-meter long ramp structures with high walls in architectural concrete quality serve as entrance and exit of the 6-km HZMB tunnel.

Project data

Location: Hongkong, China

  • East and west transitional structures with tunnel entrances and breakwaters
  • 300-meter long side walls with up to 56-meter wide ramp structures and a wall thickness of 2.50 meters.
  • 6 lanes into the tunnel portals with a longitudinal gradient of 3 %
  • Separation of the directions of traffic through reinforced concrete walls of up to 15.50 meters which serve as supports for the roofing

The 35 km long Hongkong-Zhuhai- Macao road connection is located in the area of the approach flight path of the Hong Kong International Airport, Chek Lap Kok, in an underwater tunnel. This 6 km long immersed tunnel had already been successfully built with PERI know-how – the shell construction for the east and west transitional structures was the next stage to be completed. For this, two artificial islands were created in the southern Chinese Pearl River Delta. 6 lanes lead into the two tunnel portals with a 3 % longitudinal gradient.

Hongkong-Zhuhai-Macao Bridge (HZMB) | Tunnel
Hongkong-Zhuhai-Macao Bridge (HZMB) | Operation Buildings East and West

Requirements

  • Tunnel entrances and breakwaters with highest quality requirements
  • 15.50-meter high reinforced concrete walls in SB 4 architectural concrete quality with a clearly structured joint and tie pattern, permanently waterproof

Customer

China Communications Construction Company Ltd. (CCCC)

Customer's benefit

  • Fast, safe and simple execution, planned by PERI engineers
  • Fabrication of the wall segments in regular cycle lengths of 15 meters
  • Easy moving of the formwork carriages
  • First-class architectural concrete quality
  • Most cost-effective and efficient solution by including the VARIOKIT engineering construction kit, the VARIO girder wall formwork system and SK tie technology
Portrait of Meng Fanli, Project Leader West Island, Lin Ming, Project Director, Liu Haiqing, Project Leader East Island, China Communications Construction Company Ltd. (CCCC)
Meng Fanli | Lin Ming | Liu Haiqing
Project Leader West Island | Project Director | Project Leader East Island

PERI played a decisive role in realizing this once-in-a-century structure; tunnel entrances and breakwater were extremely challenging due to maintaining the highest quality requirements. The formwork could be easily moved and provided the best possible safety and first-class architectural concrete quality. We came to appreciate the professional engineering, service and the striving of the PERI engineers for perfection.

PERI solution

  • Fast, safe and simple execution with mobile portal wall formwork carriages which can work independently, using system elements from the VARIOKIT engineering construction kit, the VARIO girder wall formwork systems and SK tie technology