Palm paper mill, United Kingdom

Palm paper mill, King’s Lynn, Great Britain - Only 7 months after beginning the excavation and foundation work, the topping-out ceremony took place; 8 months later, production started in August 2009.
Palm paper mill, King’s Lynn, Great Britain - For safe forming, reinforcement and concreting of the 9.90 m high wall, a PERI UP Rosett working scaffold was used.
Palm paper mill, King’s Lynn, Great Britain - The up to 2 m thick wall sections and columns could be economically constructed with the TRIO panel formwork.
Palm paper mill, King’s Lynn, Great Britain - For the 6.60 m high, massive reinforced concrete walls, the TRIO 330 was extended and supplemented with TRIO concreating platforms.
Palm paper mill, King’s Lynn, Great Britain - PERI UP Rosett served as shoring for the cantilevered cast in-situ concrete slab and as a working platform for placing the TRIO external formwork.
Palm paper mill, King’s Lynn, Great Britain - Modular PERI UP shoring solution providing temporary support for the 17.5 t pre-fabricated beams.
Palm paper mill, King’s Lynn, Great Britain - PERI UP site stair towers provided safe access to all working areas.

Project data

Location: King's Lynn, United Kingdom

Europe’s largest and most modern paper mill, 600 m long, 100 m wide and 30 m high

Construction period until opening: 2008 - 2009

Requirements

  • tight schedule
  • coordination of shell construction and machine assembly
  • shear walls with a thickness of 1.50 m to 2.00 m

Customer

Glass GmbH, Mindelheim, Germany

Customer's benefit

  • construction time finished three weeks before schedule
  • fast shuttering times
Palm Paper Mill Statement - Stefan Bucher, Construction Manager
Stefan Bucher
Construction Manager

In my opinion, PERI UP is two thirds faster than common scaffolding systems. On the one hand, we are able to erect it fast and safely, and on the other hand, we achieve an efficient construction sequence due to the flexibility and versatility.

PERI solution

  • optimally harmonised formwork and scaffolding solution
  • outside work scaffold for safe shuttering, reinforcement and pouring of the 9.90 m high walls
  • shoring for protruding site-mixed concrete slabs and as temporary support of the FT beams
  • scaffolding staircase access to the work places