Housing

PERI GmbH - Old Allegheny County Jail, Pittsburgh, PA, USA PERI GmbH - Old Allegheny County Jail, Pittsburgh, PA, USA PERI GmbH - Old Allegheny County Jail, Pittsburgh, PA, USA

Old Allegheny County Jail, Pittsburgh, PA, USA




PERI SKYDECK cuts Construction Time in Half Cost-effective use on a Redevelopment Project

With time and space at a minimum and no possibility to use a crane, Mascaro needed light and easy to handle formwork systems that allowed cost-effective fulfillment of the contractual requirements.

The SKYDECK System being modular in design and consisting of lightweight aluminum components allowed for rapid erection by hand as well as the flexibility of passing components through existing window openings that work required on this jobsite.

The speed of erecting and then stripping of forms amazed. With SKYDECK the crew on site was able to cut the time for forming and concrete placement operations in half.

PERI Systems In Use
  • SKYDECK Aluminium Panel Slab Formwork
  • MULTIPROP Slab prop
  • General Contractor: Mascaro Construction, Pittsburgh, PA
    Field Service: PERI USA, Pittsburgh
     
    Google +
    LinkedIn
    Twitter