Formwork and scaffolding solution quickly implemented
With the new exhibition halls, 12 and 14, the IFEMA trade fair centre in Madrid has been extended by 50.000 m² of covered exhibition space. The comprehensivePERI formwork and scaffolding solution for walls, slabs and columns could be effi ciently implemented through the supply of system equipment at short-notice.
Customized PERI slab tables allowed cost-effective construction of the 11.20 m high and up to 1.35 m thick reinforced concrete slabs. In addition, MULTIPROP aluminium slab props MP 625could be connected with MRK frames to form a modular tower system. Due to the fast moving times, savings could be made in both time and costs as well as accelerating the actual construction work.