Kröpeliner Tor Center, Rostock, Germany


Slab forming with SKYDECK brings noticeable time-savings



The Kröpeliner Tor Center is located directly in the historical centre of Rostock. Around 40 businesses and 185 car parking slots are accommodated in the four upper and two underground fl oors. In the middle of the complex, a light courtyard has been integrated in order to fl ood the shopping centre with daylight.

For construction of the 36 cm thick strong prestressed concrete slabs, the contractors decided in favour of the SKYDECK drophead. This meant that building progress could be accelerated and crane utilization kept to a minimum. With fast shuttering and striking, as well as the supply of large quantities of materials at short notice, the extremely tight construction schedule could be maintained. Up to 4,500 m² of SKYDECK as well as 8,000 MULTIPROP post shores were in use at peak times.

PERI Systems In Use
  • MULTIPROP Slab prop
  • SKYDECK Aluminium Panel Slab Formwork

  • Helmut Lemme and Karsten Teller


    Site Foremen

    “Using SKYDECK had a very positive effect on site operations. It saved valuable crane time and was always in use. PERI provided us an optimal service from planning right up to material deliveries – everything worked perfectly.“

    Contractor: ARGE KTC Rostock, Ost-Bau GmbH, Osterburg Bilfinger Berger AG, Leipzig
    Field Service: PERI Hamburg
    Field Service: PERI GmbH, Deutschland
    PERI scope 01/2007
     